Gesip initially recommended an additional 20 minutes to the 20 minutes required by law. The new post-Rouen regulations require 20% more resources in consumables: water and emulsifier.
But what happens to this recommendation made by Gesip concerning the additional 20-minute extinction of WATER & EMULSEUR consumables?
It is now necessary to talk about the 20% more consumables necessary to face the extinction of a hydrocarbon fire on site. If the site had taken the Gesip recommendation as a provision, it would be interesting to compare the quantity represented by the Gesip recommendation (+20 minutes) with the quantity represented by the +20% requested by the legislator in the text of September 24, 2020 modifying the ministerial decree of October 3, 2010.